Now that twelve different flood repair and capital project contracts are in various stages of completion, keeping track of progress is quite a task. In an effort to make the information about each contract and the project as a whole more understandable, the chart below was developed.
The data shown is as of 8/27/2008.
Project Location
Description
In Design
Bid
Let
Bid Opening
Award
Amount
Contractor
Notice to Proceed
Contractual Completion Date
% Complete
Notes
Forks of the Delaware to Locks 22/23 (Easton to Raubsville)
towpath, prism rehabilitation
complete
6/11/07
7/10/07
3/1/08
$10,720,410
Popple Construction
3/3/08
2/26/09
65%
Locks 22/23 to Bridgeton Hill Road (Raubsville to Upper Black Eddy)
towpath, prism rehabilitation
complete
5/5/08
6/17/08
7/23/08
$8,775,615
Nimaris Construction
expected 9/3/08
Bridgeton Hill to Odette's (Upper Black Eddy to New Hope)
towpath, prism rehabilitation
complete
Odette's to Ferry Road (New Hope to Lower Makefield Twp.