Friends of the Delaware Canal

Progress Report

Now that twelve different flood repair and capital project contracts are in various stages of completion, keeping track of progress is quite a task.  In an effort to make the information about each contract and the project as a whole more understandable, the chart below was developed.

The data shown is as of 8/27/2008. 

Project Location

Description

In Design

Bid
Let

Bid Opening

Award

Amount

Contractor

Notice to Proceed

Contractual Completion Date

% Complete

Notes

Forks of the Delaware to Locks 22/23 (Easton to Raubsville)

towpath, prism rehabilitation

complete

6/11/07

7/10/07

3/1/08

$10,720,410

Popple Construction

3/3/08

2/26/09

65%

Locks 22/23 to Bridgeton Hill Road (Raubsville to Upper Black Eddy)

towpath, prism rehabilitation

complete

5/5/08

6/17/08

7/23/08

$8,775,615

Nimaris Construction

expected 9/3/08

 

Bridgeton Hill  to Odette's (Upper Black Eddy to New Hope)

towpath, prism rehabilitation

complete

Odette's to Ferry Road (New Hope to Lower Makefield Twp.

towpath, prism rehabilitation

complete

3/19/08

4/17/08

5/16/08

$3,396,456

Tri-State Dredging

6/26/08

7/10/09

15%

Easton

Chain Dam and Fish Ladder repairs

complete

6/13/07

7/12/07

2/28/08

$265,664

BiState Construction

2/28/08

12/1/08

95%

Williams Twp., Raubsville, Durham

stop gate, waste gate, footbridge, other repairs

complete

3/26/08

4/29/08

5/15/08

$330,602

Bill Anskis

6/26/08

4/6/09

7%

Point Pleasant, Centre Bridge, Bowman's Hill

Locks 13 & 14, wastegate, other repairs

Lumberville

Lock 12 repair

Williams Twp.

Rocky Falls stop and waste gate repair

Reigelsville

stop and control gate repair

Easton

STP stop gate and pedestrian bridge repair

Other Projects

Lower Makefield Twp. and Yardley Borough

Black Rock Road culvert replacement

complete

3/26/09

5/15/08

6/20/08

$2,937,975

James D. Morrissey

8/20/08

9/15/09

0%